Scooby Jim provided a great deal of information in his attachment. If I may add a few comments. When aligning the...
Tuesday, April 24, 2018 01:34 PM
Thank you for your answers. I'll try to get some data with better resolution. Meanwhile i just added some more...
Tuesday, April 24, 2018 07:37 AM
I am not referring to water cooled coils, but instead to a TEAAC or TEAWC. In this case we have...
Tuesday, April 24, 2018 04:59 AM
Have a look at ABB Caldos 27, ABB supply a special version for power plants that measure the H2 to...
Monday, April 23, 2018 12:28 AM
In the design stage of a power plant, forces on entire shaft train (shear, bending, torsional etc) is calculated for...
Sunday, April 22, 2018 06:48 PM
Some people are confusing PD tests of individual bars in production with PD test of a complete winding. While the...
Friday, April 20, 2018 02:01 PM
Here are the 300 MW results
Thursday, April 19, 2018 09:19 PM
These fuses can be purchased, but lead time is 8-10 weeks, ex Houston. If John - ABB Oz, requires...
Thursday, April 19, 2018 01:43 PM
1 Mohm is very low IR for the rotor windings, there is high risk associated with such a low IR....
Thursday, April 19, 2018 07:27 AM
Second photo
Wednesday, April 18, 2018 11:00 PM